KY 32 Improvement Project in Rowan County Expected to Take Three Years; Blasting and Traffic Delays Possible

ROWAN COUNTY, Ky. — Motorists traveling along KY 32 in Rowan County can expect continued construction activity over the next several years as work progresses on a major roadway improvement project.

The Kentucky Transportation Cabinet (KYTC), Highway District 9, has released an update outlining upcoming phases of the project, including utility relocations, excavation, bridge construction, and the possibility of temporary traffic delays.

According to KYTC, the entire project is expected to take approximately three years to complete, with several construction activities scheduled to continue into spring 2027.

Utility Relocations Underway

A significant portion of the project involves relocating utilities affected by the roadway improvements.

KYTC reports that some utility relocation work has already been completed, while other portions remain underway.

Among the utilities affected are Rowan Water, Morehead Utility Plant Board sewer services, and Morehead Utility Plant Board natural gas services. Relocations involving these utilities are being performed under the highway construction contract.

Other affected utility providers are handling their own relocations, either directly or through contractors hired to perform the work.

The Transportation Cabinet provided the following updates:

  • Tennessee Gas Pipeline: Relocation work has recently been completed.

  • Overhead Utilities: Relocation activities are expected to continue over the next three to four months.

  • Water, Sewer, and Gas Distribution: Relocation work will continue throughout the duration of the roadway project.

Residents experiencing interruptions or other issues with their utility services are encouraged to contact their respective utility providers directly.

Bridge Construction and Excavation Work

Construction will continue on the Pennington Flats Road bridge over Big Brushy Creek.

Meanwhile, excavation activities are scheduled to begin in the area between Copperas Hollow Road and Limestone Road.

According to KYTC, contractors will use articulated off-road trucks to transport excavated material from the construction area.

These trucks will cross KY 32 and Big Brushy Creek, using a temporary creek crossing, before delivering the material to the site of a former automobile salvage yard.

The Transportation Cabinet clarified that most of the earthwork completed to date has involved clearing and grubbing, rather than actual excavation.

Clearing and grubbing generally involves removing trees, brush, vegetation, and other surface obstacles to prepare an area for construction.

The upcoming excavation phase will involve removing and transporting earth and other material as work progresses.

Blasting Could Cause Temporary Traffic Delays

One aspect of the project that motorists should be aware of is the possibility of blasting operations.

KYTC says the construction contractor may use blasting during portions of the excavation work.

If blasting becomes necessary, motorists could experience temporary traffic delays of up to approximately 15 to 20 minutes.

The Transportation Cabinet has not indicated that blasting will definitely occur, only that it remains a possible method of completing certain excavation activities.

Multiyear Project Will Continue into 2027 and Beyond

KYTC estimates that the overall KY 32 improvement project will take approximately three years to complete.

Construction activities currently planned into spring 2027 include continued work on the Pennington Flats Road bridge and excavation between Copperas Hollow Road and Limestone Road.

The spring 2027 timeframe does not represent the anticipated completion of the entire project.

As construction progresses, motorists traveling through the affected areas should remain alert for construction equipment, trucks crossing the highway, changing traffic conditions, and possible delays.

Drivers are encouraged to use caution when traveling through construction zones and allow additional travel time when necessary.

Source: Kentucky Transportation Cabinet, Highway District 9, official project update.